NTPC's subsidiary NVVN declared its first 250 MW / 500 MWh BESS project commercial from 27 October 2026, with power scheduling starting 28 October. This is a commercial operation start for a new energy storage asset.
NTPC's step-down subsidiary, NGEL, declared commercial operation of 153.94 MW solar capacity in Bikaner, Rajasthan. This increases NTPC Group's total commercial capacity to 90,376 MW.
NTPC's subsidiary, NTPC Green Energy Limited, announced the commercial operation of 64.76 MW capacity at the Khavda Solar PV Project. This increases total capacity to 10,786.56 MW.
NTPC subsidiary THDC India successfully commissioned a 11 MWac floating solar plant. This increases NTPC group's total installed capacity to 90,965 MW.
NTPC’s subsidiary declared commercial operation of 50.4 MW Vanki Wind project on 8 July 2026. Group’s total installed capacity now stands at 90,954 MW.
NTPC declared commercial operation of 50 MW solar capacity, raising group capacity to 90,857 MW. This expands its renewable portfolio and operational base.
NTPC declared commercial operations for its 105 MW Khavda-II solar project in Gujarat. Total group installed capacity now reaches 90,773 MW, boosting operational revenue visibility.
NTPC declared commercial operation for 100 MW of its 176 MW Solar PV Project at Ramagundam, Telangana, effective May 2, 2026. This addition brings the group's total installed capacity to 89,805 MW and commercial capacity to 88,725 MW, highlighting the company's progress in expanding its renewable energy portfolio.
NTPC Ltd's subsidiary, NTPC Green Energy Limited, has declared the commercial operation of 87.50 MW solar capacity in Rajasthan. This addition brings the NTPC group's total installed capacity to 89,615 MW and commercial capacity to 88,535 MW, effective April 19, 2026.
NTPC announced the commercial operation of a 150 MW solar project in Rajasthan through its subsidiary, NTPC Green Energy Limited. This addition increases the NTPC group's total installed capacity to 89,528 MW and commercial capacity to 88,448 MW, effective April 18, 2026.
NTPC's subsidiary, THDC India Limited, declared the Commercial Operation Date for the 4th unit (250 MW) of the Tehri PSP project effective April 12, 2026. This addition brings NTPC group's total installed capacity to 89,378 MW and commercial capacity to 88,298 MW, strengthening its operational footprint in the power sector.