H1 FY27 consolidated revenue rose about 39%, EBITDA about 40% and PAT 40%. Part of the revenue growth is metal pass-through. Management expects margins to dip as low-margin assembly scales, and its growth outlook is hedged.
Shivalik Bimetal Controls declared an interim dividend of Re 1 per share for FY 2026-27 with record date 13-Nov-2026. It also recommended a 2:1 bonus issue, with AGM/postal ballot fixed for 16-Dec-2026.
Shivalik Bimetal recommended a 2:1 bonus issue and declared a Rs 1 interim dividend. Shareholder approval is due at a 16 December 2026 AGM or postal ballot.
Shivalik Bimetal Controls reported a 62% YoY increase in Q2 FY27 consolidated EBITDA to ₹50.2 crore. Consolidated revenue grew 43.9% to ₹197.8 crore during the same period.
Shivalik Bimetal added a bonus share proposal and interim dividend to its 04 November 2026 board agenda. Trading window remains closed until 06 November 2026.
Shivalik Bimetal Controls intimated a board meeting on 4 November 2026 to consider unaudited standalone and consolidated results for the quarter ended September 2026. This is advance notice only; no results are reported yet.
The company submitted its quarterly shareholding pattern for the period ending September 30, 2026, confirming the recent reclassification of a promoter entity.
Shareholders approved an amendment to the Articles of Association of Shivalik Bimetal Controls Limited to enable future capital raising initiatives. This is an enabling provision only.
Shivalik Bimetal Controls held its 42nd Annual General Meeting on September 2, 2026. The meeting transacted ordinary and special business, including the re-appointment of a director.
Shivalik Bimetal Controls reported a Code of Conduct violation under SEBI Insider Trading regulations by a former employee's relative. The audit committee is reviewing the incident.
Shivalik Bimetal Controls received 'No Objection Certificates' from BSE and NSE for the reclassification of Solan Developers Private Limited from the promoter to public category.
Shivalik Bimetal Controls Limited received regulatory approvals for setting up its Pune Facility Phase II. This authorization enables the company to proceed with planned facility expansion.
Shivalik Bimetal Controls Ltd has received regulatory approvals for its Phase II facility in Pune. This milestone marks a step in the company's planned capacity expansion.
Shivalik Bimetal Controls is in the process of obtaining necessary approvals for setting up its Pune facility (Phase-II). This is an ongoing project status update.
Shivalik Bimetal Controls Limited has executed a loan agreement to provide an unsecured loan of ₹11 Crore to its wholly-owned subsidiary, Shivalik Engineered Products Pvt. Ltd.
SBCL delivered strong Q1FY27 performance with revenue up 33.4% YoY. Strategy focuses on shifting from commodity strips to high-value components and assemblies in EV, smart meter, and switchgear segments.
Shivalik Bimetal Controls Limited has scheduled its 42nd AGM for September 02, 2026. The company fixed August 26, 2026, as the record date for a Rs. 2 final dividend.
Shivalik Bimetal Controls Limited has released its Annual Report for FY 2025-26. The 42nd AGM is scheduled for September 02, 2026, with a final dividend of Rs. 2 per share.
SBCL reported strong Q1FY27 performance with revenue up 33% and PAT up 45% YoY. Strategy focuses on high-value integrated solutions like PCBA and busbars for EVs and smart meters.
The subsidiary, Shivalik Bimetal Engineers Private Limited, announced the resignation of its statutory auditor, Arora Gupta & Co., citing increased audit resource requirements.
Mr. Rajeev Ranjan has resigned as the Chief Financial Officer of Shivalik Bimetal Controls Limited, effective from the close of business hours on October 31, 2026.
Shivalik Bimetal Controls Limited announced that M/s Arora Gupta & Co. resigned as statutory auditors for its wholly-owned subsidiaries, effective August 6, 2026.
Shivalik Bimetal Controls Limited has scheduled a board meeting for August 6, 2026, to consider and approve its financial results for the quarter ended June 30, 2026.
Shivalik Bimetal Controls Ltd has filed its quarterly shareholding pattern for the period ended June 30, 2026. This disclosure provides details on share distribution across investor categories.
Shivalik Bimetal received Consent to Operate for its Pune Phase-I facility. This enables commercial production of value-added components for the automotive electrification market.
Shivalik Bimetal Controls received Consent to Operate for its Pune Facility (Phase-I) from MPCB. This regulatory approval allows the company to proceed with operations at the site.