L&T secured two Large-band government construction orders in Delhi and Amaravati totalling 70.3 lakh sq ft. The EPC and design-build contracts fall in the ₹2,500–5,000 Crore band.
Value
₹2,500 Cr
From
Central Public Works Department; Government of Andhra Pradesh
L&T received an LNTP for the New Tashkent International Airport passenger terminal in Uzbekistan. The 17-million-passenger project initiates pre-construction activities under its EPC contract.
From
PPP consortium developing the New Tashkent International Airport, Uzbekistan
L&T secured an LNTP from DVC CIL Power for the 2×800 MW Chandrapura thermal plant main package in Jharkhand. The contract value is undisclosed; execution timeline is not stated.
L&T secured an LNTP from DVCCIL for the 1,600 MW Chandrapura thermal power plant. The Major-classified order (₹5,000+ Cr) covers full main plant scope.
Larsen & Toubro's Power Transmission & Distribution business secured multiple 'Mega' EPC orders across India, Saudi Arabia, and the UAE. The aggregate value is at least ₹10,000 Crore.
Value
₹10,000 Cr
From
Multiple clients including a leading private sector developer in India
Larsen & Toubro secured twin contracts from Dubai’s Roads and Transport Authority to develop the Latifa Bint Hamdan Corridor, with project completion expected by 2028.
Larsen & Toubro's Transportation Infrastructure vertical won two contracts from Dubai's RTA for the Latifa Bint Hamdan Corridor. The orders are classified as 'large' and 'significant'.
L&T secured a large EPCIC offshore order from ONGC for ADR-I and NLM-14 projects. Scope covers three well-head platforms, one riser platform, and subsea pipelines.
L&T won a Large offshore EPCIC order from ONGC for Ratna-I and NLM-14. The Rs. 2,500+ Crore contract covers three well-head platforms and subsea pipelines.
Larsen & Toubro's Renewables vertical secured a major order to develop three Battery Energy Storage System projects in the Middle East, totaling 6 GWh capacity.
Larsen & Toubro secured a large contract from Dubai Aviation Engineering Projects for an Automated People Mover system. The order value is between ₹2,500 and ₹5,000 Crore.
L&T secured an 'Ultra-Mega' offshore development order from a Middle East client. The scope includes full EPCIC services, though the contract value remains undisclosed.
Larsen & Toubro's hydrocarbon unit secured an ultra-mega order for a strategic offshore development project in the Middle East. The contract is valued at over ₹15,000 Crore.
L&T secured a Mega order through a partnership with Together AI to build India's largest NVIDIA B300 AI Factory. The project involves deploying 10,000 NVIDIA GPUs.
Larsen & Toubro's hydrocarbon unit secured multiple offshore contracts from ONGC for pipeline replacement and wellhead platforms. The projects involve EPCIC of subsea segments and four platforms.
Larsen & Toubro secured a Limited Notice to Proceed from NTPC for the Lara Stage-III project. The contract covers two 800 MW ultra-supercritical units.