JSW Energy reached a total installed capacity of 15.1 GW, adding 1,694 MW since April 2026. This milestone reflects progress in its growing renewable energy portfolio.
JSW Energy's subsidiary has contracted Toshiba JSW for 1,600 MW of steam turbine generators. This Phase II order completes equipment procurement for the 3,200 MW Salboni Thermal Project.
JSW Energy has increased its total installed capacity to 14,920 MW, following the addition of 1,166 MW renewable and 300 MW inorganic thermal capacity since April 2026.