23 Oct 2026
18:40 IST
BSE
Capacity Expansion CG Power and Industrial Solutions Ltd CGPOWER
CG Power board approved an additional Rs.9.45 Crore capex for its Vilholi GIS brownfield project. The enhancement adds 240 equivalent bays, funded by internal accruals.
Value ₹9.45 Cr
Execution 3-6 months
GIS testing and manufacturing capacity 240.0 Eq Bays
23 Oct 2026
18:38 IST
BSE
Capacity Expansion CG Power and Industrial Solutions Ltd CGPOWER
CG Power board approved Rs.15.31 Crore to add 3,600 EHV circuit breaker units annually. Completion is expected within 6-9 months, funded by internal accruals.
Value ₹15.31 Cr
Execution 6-9 months
EHV circuit breaker manufacturing capacity 3600.0 units/year
23 Oct 2026
18:37 IST
BSE
Capacity Expansion CG Power and Industrial Solutions Ltd CGPOWER
CG Power plans a Rs.300 Crore investment adding 4,236 units of annual capacity at Ambad. Production is expected within 30-36 months.
Value ₹300.0 Cr
Execution 30-36 months
OIP bushings and instrument transformer manufacturing capacity 4236.0 equivalent units/year
23 Oct 2026
18:34 IST
BSE
Capacity Expansion CG Power and Industrial Solutions Ltd CGPOWER Alfa AlertAn Alfa Alert is ALFA Finder's top-priority alert: filings that can move a stock, such as orders, fund raises and approvals, sent to subscribers on Telegram within seconds of reaching the exchange.
CG Power board approved a 10,000 MVA power transformer capacity expansion costing Rs.68 Crore. Completion is planned within 12-15 months, funded by internal accruals.
Value ₹68.00 Cr
Execution 12-15 months
power transformer manufacturing capacity 10000.0 MVA
8 Sep 2026
14:08 IST
NSE
Capacity Expansion CG Power and Industrial Solutions Ltd CGPOWER Alfa AlertAn Alfa Alert is ALFA Finder's top-priority alert: filings that can move a stock, such as orders, fund raises and approvals, sent to subscribers on Telegram within seconds of reaching the exchange.
CG Power adds 45,000 MVA transformer capacity at T5 for ₹792 Crore via QIP. Total capacity reaches 1,20,000 MVA to serve renewables and data centers.
Value ₹792.0 Cr
Execution Phased commissioning from Oct 2025 to full capacity
transformer manufacturing capacity 45000 MVA
24 Jul 2026
17:10 IST
NSE