Ceigall subsidiary achieved financial close for its Rs. 2,160 Crore NH 139-W highway project in Bihar. The 78.9 km project has a 730-day execution period.
Ceigall received a Completion Certificate for the NH-709B Delhi-Saharanpur six-lane highway in Uttar Pradesh. The EPC project is declared fit for operation as of September 2024.
Ceigall India Limited announced that the tender, for which it was previously the L1 bidder, has been cancelled by the Delhi PWD. The project is no longer active.
Ceigall India Ltd disclosed a Rs.1,305 Crore 6‑lane highway project under the Hybrid Annuity Model, appointed on 06‑07‑2026. The subsidiary Ceigall VRK 12 Pvt Ltd will execute it.
Ceigall India achieved its 35% project milestone for the Ayodhya Bypass project 92 days ahead of schedule. This development demonstrates strong execution efficiency on site.