| Revenue growth | Standalone -2% YoY; +5% QoQ |
|---|---|
| Margins | Standalone EBITDA 13.81% vs 11.25% YoY; PBT margin 10.65% |
| Order book | Standalone ₹15,369 Cr; incl JVs ₹28,695 Cr; 4,955 wagons ordered Q2 |
| Demand visibility | Order book ₹15,369 Cr standalone; 9,144 wagons outstanding |
Growth
Standalone revenue ₹773 Cr (-2% YoY); PRS +146% to ₹300 Cr, FRS -29%. PAT ₹63 Cr (+34% YoY).
Outlook
FY27 metro output 200–220 coaches; Vande Bharat prototype testing Q4 FY27; forged wheels commercial Dec 2026.
Risks
FRS revenue -29% YoY; wagon dispatches 1,155 vs 1,872; H1 working-capital outflow ₹70 Cr; borrowings up ~₹244 Cr since March.
Investor Presentation filed with BSE, NSE: TITAGARH. Summary written with AI assistance from the document.
Titagarh Rail Systems Ltd: key numbers
- Share price
- ₹737.15
- Market cap
- ₹9,927 Cr
- Revenue (annual)
- ₹3,186 Cr
- Net profit (annual)
- ₹122.8 Cr
- P/E (TTM)
- 45.7×Sector 33.1×
- Promoter holding
- 40.46%+0.00% QoQ
- FII holding
- 11.39%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Titagarh Rail Systems Ltd
All →Titagarh Rail Systems Earnings Call Transcript: Key Takeaways
Q2 FY27 metro execution improved and wagon visibility was restored via the option order, but no revenue or profit was disclosed. Management hedged on timelines, withheld project-level figures, and deflected margin and tender questions.
Titagarh Rail Systems Other Announcement
Titagarh Rail Systems filed CARE's quarterly monitoring report on its Rs 199.99 crore warrant proceeds. No funds were utilised and no deviations were found.
Titagarh Rail Systems Q2 FY27 Results: Net Profit ₹63.2 Cr, Up 49.1% YoY
Titagarh Rail Systems Ltd reported revenue from operations of ₹792.6 Cr (-0.8% YoY) and net profit of ₹63.2 Cr (+49.1% YoY) for Q2 FY27.
- Key figure
- Net profit ₹63.2 Cr · +49.1% YoY
Titagarh Rail Systems Board Meeting Date
Titagarh Rail Systems will consider half-yearly results for September 2026 at a board meeting on 10 November. Trading window closes from 1 October until 13 November 2026.
Titagarh Rail Systems Order Update: ₹1,717 Cr
Titagarh Rail received an additional 4,955 BOXNHL wagon order from the Ministry of Railways, valued at ₹1,716.90 Crore plus GST. The amended contract now totals ₹10,404.10 Crore including GST.
- Value
- ₹1,717 Cr
- From
- Ministry of Railways
- Execution
- 222 days from the amendment date, up to 07.06.2027
Titagarh Rail Systems Board Meeting Date
Titagarh Rail Systems scheduled a board meeting for 29 October 2026 to approve unaudited financial results. The trading window remains closed until 48 hours post-results.