| Value | ₹428.6 Cr |
|---|---|
| Order from | Ultratech Cement Ltd; Jujhar Logistics & Travels Ltd; APL Logistics Vascor Automotive Pvt Ltd |
| Execution period | Order 1 (Ultratech): first rake within 5 months, all by 28 Feb 2027; Order 2 (Jujhar): on or before 31 Dec 2027; Order 3 (APL): phased delivery |
BSE filing, NSE: TEXRAIL. Summary written from the filing by ALFA Finder's alert engine.
Texmaco Rail & Engineering Ltd: key numbers
- Share price
- ₹103.55
- Market cap
- ₹4,213 Cr
- Revenue (annual)
- ₹4,377 Cr
- Net profit (annual)
- ₹195.2 Cr
- P/E (TTM)
- 16.1×Sector 33.1×
- Promoter holding
- 48.34%+0.00% QoQ
- FII holding
- 6.02%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Texmaco Rail & Engineering Ltd
All →Texmaco Rail & Engineering Management Change
Texmaco Rail & Engineering has re-appointed Mr. Udyavar Vittal Kamath as an Executive Director (WTD) with effect from 1 February 2027 for a 12-month term. The filing is a Regulation 30 management change disclosure.
- Execution
- 12 months from 1 February 2027
Texmaco Rail & Engineering Q2 FY27 Results: Net Profit ₹111 Cr, Up 73.7% YoY
Texmaco Rail & Engineering Ltd reported revenue from operations of ₹867.7 Cr (-31.0% YoY) and net profit of ₹111 Cr (+73.7% YoY) for Q2 FY27.
- Key figure
- Net profit ₹111 Cr · +73.7% YoY
Texmaco Rail & Engineering Credit Rating
Crisil Ratings assigned Texmaco Rail & Engineering a long-term bank facilities rating of Crisil A+/Stable. The rating is disclosed under Regulation 30.
Texmaco Rail & Engineering Board Meeting Date
Texmaco Rail & Engineering will hold a board meeting on November 5, 2026 to consider unaudited standalone and consolidated results for Q2 and H1 FY27. No financial figures are disclosed in this intimation.
Texmaco Rail & Engineering Order Update: ₹412.3 Cr
Ministry of Railways added 1,020 BOXNS wagons (₹412.32 Crore) to Texmaco Rail's existing contract via option clause. Amended total value: ₹1,786.74 Crore, delivery by June 2027.
- Value
- ₹412.3 Cr
- From
- Ministry of Railways
- Execution
- 162 days beyond re-fixed DP, i.e. up to 11.06.2027
Texmaco Rail & Engineering Other Announcement
Texmaco Rail & Engineering Ltd has filed its quarterly shareholding pattern as mandated by SEBI regulations. This report provides the current status of equity distribution.
Other new order win announcements
All →Airfloa Rail Technology Bags ₹4.12 Cr Order from Furnishing Division, Integral Coach Factory, Chennai
Airfloa Rail Technology received a Rs.4.12 Crore order from Integral Coach Factory's Furnishing Division. Completion is due by February 4, 2027.
- Value
- ₹4.12 Cr
- From
- Furnishing Division, Integral Coach Factory, Chennai
- Execution
- On or before 04/02/27
NLC India Bags New Order from SJVN Limited
NLC India's subsidiary NIRL executed a PPA with SJVN for 100 MW of its 200 MW wind project. Scheduled commencement of supply is by November 2028.
- From
- SJVN Limited
- Execution
- Scheduled Commencement of Supply Date by 03.11.2028
- wind power capacity (PPA-covered)
- 100.0 MW
Kwick Forensic Solutions Bags ₹2.53 Cr Order from Forensic Science Department, Chennai
Kwick Forensic Solutions won two orders from Forensic Science Department, Chennai, worth Rs 2.53 Crore including GST. Genetic Analyser supply is due by February 4, 2027.
- Value
- ₹2.53 Cr
- From
- Forensic Science Department, Chennai
- Execution
- 3 months from date of purchase order, by 04/02/2027
Ashoka Buildcon Bags ₹865.9 Cr Order from National Highways Authority of India
Ashoka Buildcon was declared L1, the lowest bidder, for an NHAI Expressway EPC project in Gujarat. The quoted EPC price is Rs.865.90 Crore excluding GST, to be executed over 18 months.
- Value
- ₹865.9 Cr
- From
- National Highways Authority of India (NHAI)
- Execution
- 18 months
Danish Power Bags ₹38.76 Cr Order from Leading Renewable Energy IPP/EPC Company
Danish Power won a Rs.38.76 Crore order for Inverter Duty Transformers from an unnamed renewable IPP/EPC firm. Execution is due within 6-12 months.
- Value
- ₹38.76 Cr
- From
- Leading Renewable Energy IPP/EPC Company
- Execution
- 6-12 months
Skytech Infinite Platform Bags ₹1.3 Cr Order from Intermittent Contractor; identity withheld under NDA
Skytech Infinite Platform won a Rs 1.30 Crore order to supply FLP electrical panels and wiring. Delivery is due in six months at a Bengaluru Rural site.
- Value
- ₹1.30 Cr
- From
- Intermittent (OEM) Contractor; identity withheld under NDA
- Execution
- Approximately 6 months