NSE filing, NSE: LLOYDSME. Summary written from the filing by ALFA Finder's alert engine.
Lloyds Metals & Energy Ltd: key numbers
- Share price
- ₹1,818.00
- Market cap
- ₹1,02,362 Cr
- Revenue (annual)
- ₹17,113 Cr
- Net profit (annual)
- ₹3,681 Cr
- P/E (TTM)
- 19.5×Sector 17.1×
- Promoter holding
- 61.61%-0.02% QoQ
- FII holding
- 1.93%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Lloyds Metals & Energy Ltd
All →Lloyds Metals & Energy Debt & Borrowing: ₹680 Cr
Lloyds Metals approved allotment of 68,000 senior secured NCDs worth Rs. 680 Crore on a private placement basis. The 9% debentures mature October 2029 and carry a Crisil AA/Stable rating.
- Value
- ₹680.0 Cr
- Execution
- Approximately 3 years from the deemed date of allotment, maturing 29 October 2029
Lloyds Metals & Energy Earnings Call Transcript: Key Takeaways
Record H1 with 38.33% standalone EBITDA margin, but Q2 softened on monsoon and coal costs. Shemaf debt relief, copper ramp-up and Suria ore supply remain unresolved.
Lloyds Metals & Energy Acquisition Worth ₹625 Cr
Lloyds Metals and Energy agreed to acquire Thriveni Earthmovers and Infra Private Limited for up to Rs 625 Crore in cash. The deal is expected to complete during FY 2026-27 in tranches.
- Value
- ₹625.0 Cr
- Execution
- FY 2026-27
Lloyds Metals & Energy Fund Raise
Lloyds Metals and Energy's board approved a fund raise, with the mode of financing yet to be decided. Investors should watch for the eventual issuance structure and size.
Lloyds Metals & Energy Capacity Expansion
Lloyds Metals and Energy board approved a new 360 MW thermal power plant at Konsari, Maharashtra. Completion is targeted for March 2029, subject to approvals.
- Execution
- Expected completion by March 2029, subject to regulatory and statutory approvals
- thermal power capacity
- 360.0 MW
Lloyds Metals & Energy Capacity Expansion: ₹3,240 Cr Investment
Lloyds Metals and Energy approved setting up a new 2 × 180 MW (360 MW) thermal power plant at Konsari, Maharashtra. Investment is Rs.3,240 Crore, with completion expected by March 2029.
- Value
- ₹3,240 Cr
- Execution
- Expected completion by March 2029, subject to regulatory and statutory approvals
- thermal power generation capacity
- 360.0 MW
Other annual report announcements
All →Mrugesh Trading Annual Report
Mrugesh Trading submitted its FY2025-26 Annual Report for the 42nd AGM to be held on 30 September 2026. The filing contains the full annual report, including financials and governance disclosures.
Generic Engineering Construction and Projects Annual Report
Generic Engineering filed its FY2025-26 Annual Report ahead of its 32nd AGM on 30 November 2026. The filing covers board changes and a planned bank-funded EPC expansion.
Vineet Laboratories Annual Report
Vineet Laboratories filed its FY 2025-26 Annual Report, which marks its turnaround and recapitalisation year. The AGM is scheduled for 30 November 2026.
Indrayani Biotech Annual Report
Indrayani Biotech has filed its 34th Annual Report for FY2025-26, containing the AGM notice for 30 November 2026 by VC/OAVM. The chairman notes a Rights Issue was initiated in October 2026 to raise capital.
ESDS Software Solution Annual Report
ESDS Software Solution submitted its FY2025-26 Annual Report along with the AGM notice. The AGM is on 30 November 2026 via VC/OAVM, with remote e-voting.
The Orissa Minerals Development Company Annual Report
Orissa Minerals Development Company filed its FY 2025-26 Annual Report and 108th AGM notice, with the AGM set for 30 November 2026. The filing is a Regulation 34 intimation with no transaction or financial event.