| Metric | Q2 FY27 | Q1 FY27 | Q2 FY26 |
|---|---|---|---|
| Revenue from operations | 78749.9 | 67941.7 | 67983.5 |
| Other income | 2306.3 | 2376.7 | 1384.3 |
| Total income | 81056.2 | 70318.5 | 69367.8 |
| Profit before exceptional items & tax | 7641.1 | 6922.3 | 6336.1 |
| Profit before tax | 7641.1 | 6922.3 | 6336.1 |
| Net profit | 5949.1 | 4988.0 | 4678.0 |
| Operating margin | 9.4% | 9.8% | 9.1% |
A dash means the filing did not report that period; n/m means not meaningful (margin on near-zero revenue). Growth is not shown when either period was a loss. Operating profit excludes other income.
| Net profit, year on year | +27.20% |
|---|---|
| Net profit, quarter on quarter | +19.30% |
| Revenue, year on year | +15.80% |
| Operating profit, year on year | +7.70% |
| Operating profit, quarter on quarter | +17.40% |
NSE results filing, NSE: LT. Figures extracted from the filing.
Larsen & Toubro Ltd: key numbers
- Share price
- ₹3,801.30
- Market cap
- ₹5,34,821 Cr
- Revenue (annual)
- ₹2,85,874 Cr
- Net profit (annual)
- ₹16,084 Cr
- P/E (TTM)
- 29.9×Sector 31.7×
- Promoter holding
- 0.00%+0.00% QoQ
- FII holding
- 19.22%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Larsen & Toubro Ltd
All →Larsen & Toubro Investor Presentation: Key Takeaways
Q2 FY27 record order inflow ₹1477bn (+28%), revenue ₹787.5bn (+16%), PAT ₹52bn (+33%); EBITDA margin compressed to 8.7%.
Larsen & Toubro Employee Stock Options
L&T's NRC approved allotment of 21,098 equity shares to employees who exercised stock options. The shares rank pari-passu with existing equity.
Larsen & Toubro Bags ₹5,000 Cr Order from Dhaka Mass Transit Company Limited
L&T won Major orders (₹5,000-10,000 Cr) for two Dhaka Metro Line 1 packages from DMTCL. The JICA-funded project spans 31 km with 19 stations.
- Value
- ₹5,000 Cr
- From
- Dhaka Mass Transit Company Limited (DMTCL)
- metro track length
- 31 km
Larsen & Toubro Bags ₹2,500 Cr Order from Central Public Works Department; Government of Andhra Pradesh
L&T secured two Large-band government construction orders in Delhi and Amaravati totalling 70.3 lakh sq ft. The EPC and design-build contracts fall in the ₹2,500–5,000 Crore band.
- Value
- ₹2,500 Cr
- From
- Central Public Works Department; Government of Andhra Pradesh
- Execution
- 24 months (Delhi) + 30 months (Amaravati)
- built-up area
- 70.3 lakh sq ft
Larsen & Toubro Bags New Order from PPP consortium developing the New Tashkent International Airport,...
L&T received an LNTP for the New Tashkent International Airport passenger terminal in Uzbekistan. The 17-million-passenger project initiates pre-construction activities under its EPC contract.
- From
- PPP consortium developing the New Tashkent International Airport, Uzbekistan
- airport passenger capacity
- 17 MPPA
Larsen & Toubro Business Update
L&T commenced pre-construction activities under a previously-awarded EPC contract for the New Tashkent International Airport. The project, in the Ultra-Mega band, will serve ~17 million passengers annually.
- From
- PPP consortium developing New Tashkent International Airport, Uzbekistan
- airport passenger capacity
- 17 MPPA