BSE filing, NSE: HIKAL. Summary written from the filing by ALFA Finder's alert engine.
Hikal Ltd: key numbers
- Share price
- ₹202.10
- Market cap
- ₹2,492 Cr
- Revenue (annual)
- ₹1,713 Cr
- Net profit (annual)
- ₹-48.80 Cr
- P/E (TTM)
- -73.7×Sector 46.1×
- Promoter holding
- 68.85%+0.00% QoQ
- FII holding
- 1.28%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Hikal Ltd
All →Hikal Other Announcement
Hikal Ltd filed its quarterly shareholding pattern for the period ended 30 September 2026. The filing reports routine ownership data with no new transaction.
Hikal Board Meeting Date
Hikal's board meets November 3, 2026 to consider September quarter and half-year results. The results are yet to be approved.
Hikal Other Announcement
Hikal Ltd filed its quarterly shareholding pattern for the period ending September 30, 2026, as required under SEBI Regulation 31(1)(b).
Hikal Management Change
Hikal Limited announced the cessation of Mr. Jai Hiremath as Executive Chairman and the resignation of Mrs. Sugandha Hiremath. Mr. Anish Swadi was appointed as CEO-Animal Health.
Hikal Other Announcement
Hikal Ltd. has been assigned an ESG rating of "Crisil ESG 65" by Crisil ESG Ratings & Analytics Limited, based on their independent assessment of public data.
Hikal Annual General Meeting
Hikal Ltd held its 38th AGM on September 23, 2026, approving financial statements, director appointments, remuneration revisions, and declaring a total dividend of ₹0.60 per share.
Other production started announcements
All →EPack Prefab Technologies Production Started
EPACK Prefab commenced commercial production at its Ghiloth, Rajasthan facility effective October 28, 2026, adding 11,300 MT/annum of PEB capacity and 8,00,000 sq m/annum of PUF capacity. The project cost of around INR 100 Crore is not treated as an event value.
- PEB structures manufacturing capacity
- 11300.0 MT/annum
Zelio E-Mobility Production Started
Zelio E-Mobility began commercial production at its new Patan, Hisar plant on October 28, 2026. The plant adds 72,000 annual units of two- and three-wheeler capacity.
- manufacturing capacity (two- and three-wheelers)
- 72000.0 units per annum
Subros Production Started
Subros started commercial production at its new Kharkhoda greenfield plant on 28 October 2026. The plant adds 4.5 lakh units per annum of HVAC and hose capacity.
- HVAC and hose & tubes manufacturing capacity
- 4.5 lakh units per annum
ACME Solar Holdings Production Started
ACME Solar's subsidiary commissioned 35.77 MW/143.08 MWh of BESS capacity, bringing cumulative commissioned capacity to 195.35 MW/781.40 MWh. Commercial operation is scheduled for October 29, 2026.
- BESS discharge capacity commissioned
- 35.77 MW
Kalana Ispat Production Started
Kalana Ispat has commenced commercial production of alloy steel round bars at its new Khengaria rolling mill. The mill has an annual capacity of about 65,000 MT.
- alloy steel rolling mill capacity
- 0.065 MTPA
Jainik Power Cables Production Started
Jainik Power Cables commissioned a 400 kW solar plant at its Sonipat facility in October 2026. The installation supports energy efficiency and its ESR sustainability commitments.
- solar power plant capacity
- 400 kW