| Management target | Revenue 2030 |
|---|
| Revenue growth | Q2 +25% YoY; H1 +29% YoY |
|---|---|
| Margins | Q2 EBITDA 12.0% vs 19.1% in Q1 |
| Demand visibility | Pellet sales +42% YoY in Q2 |
| Management confidence | Expects margin recovery from Q4FY27 |
Growth
H1FY27 revenue Rs 3,382 Cr (+29% YoY) on higher volumes and realisations. H1 PAT Rs 307 Cr (-19%), EBITDA margin 15.7%.
Outlook
Margin recovery expected from Q4FY27 via captive ore. Beneficiation plant Q3FY27, 20 GWh BESS Q1FY28, CRM Dec'27. Vision 2030: 4x revenue, 3x EBITDA and PAT.
Risks
Iron ore mining volumes down 24% in H1 on overburden space constraints. Costlier market ore and coal amid West Asia crisis.
Investor Presentation filed with BSE, NSE: GPIL. Summary written with AI assistance from the document.
Godawari Power & Ispat Ltd: key numbers
- Share price
- ₹226.69
- Market cap
- ₹15,268 Cr
- Revenue (annual)
- ₹5,381 Cr
- Net profit (annual)
- ₹800.8 Cr
- P/E (TTM)
- 20.9×Sector 17.0×
- Promoter holding
- 63.17%-0.01% QoQ
- FII holding
- 5.36%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Godawari Power & Ispat Ltd
All →Godawari Power & Ispat Regulatory Approval
Godawari Power and Ispat received forest permission to fell trees on 60.84 hectares for mine overburden dumping. The approval supports its Ari Dongri iron ore mining.
- iron ore mining capacity
- 6.0 MTPA
Godawari Power & Ispat Business Update
Godawari received forest clearance for tree felling on 60.84 hectares at Ari Dongri mines. This enables iron ore mining at full 6 MTPA capacity.
- iron ore mining capacity
- 6.0 MTPA
Godawari Power & Ispat Earnings Call Transcript: Key Takeaways
Revenue grew 25% YoY to ₹1,632 Cr, but profitability is under severe pressure due to elevated iron ore and coal costs.
Godawari Power & Ispat Capacity Expansion: ₹110 Cr Investment
Godawari Power approved Rs.110 Crore additional investment in wholly owned subsidiary GNEPL. Funds will build a 3 GWh battery storage manufacturing line by March 2028.
- Value
- ₹110.0 Cr
- Execution
- Construction from March 2027; investment to be completed and commissioning targeted by March 2028.
- manufacturing capacity (C&I energy storage)
- 3.0 GWh
Godawari Power & Ispat Capital Structure Change
Godawari Power's subsidiary GNEPL allotted Rs 50 crore of preference shares to the parent on November 12, 2026. The funds will finance a battery storage project.
- Value
- ₹50.00 Cr
Godawari Power & Ispat Other Announcement
Godawari Power & Ispat unveiled a new corporate logo and brand identity at its Q2 board meeting. The rebrand unifies the group under the 'ONE Godawari' vision.