| Execution period | March 2026 |
|---|
BSE filing, BSE: 543971. Summary written from the filing by ALFA Finder's alert engine.
Bondada Engineering Ltd: key numbers
- Share price
- ₹279.00
- Market cap
- ₹3,116 Cr
- Revenue (annual)
- ₹2,843 Cr
- Net profit (annual)
- ₹203.5 Cr
- P/E (TTM)
- 15.3×Sector 31.3×
- Promoter holding
- 61.52%+0.00% QoQ
- FII holding
- 0.44%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from Bondada Engineering Ltd
All →Bondada Engineering SME to Main Board Migration
Bondada Engineering received NSE listing approval for migration from BSE SME to NSE Main Board. The milestone broadens investor reach and supports long-term growth.
Bondada Engineering Bags ₹219.9 Cr Order from Gujarat Industries Power Company Ltd
Bondada Engineering secured an order worth ₹219.88 Crore from GIPCL for a 20 MW/120 MWh BESS project, to be executed over 18 months.
- Value
- ₹219.9 Cr
- From
- Gujarat Industries Power Company Ltd
- Execution
- 18 months
- BESS capacity
- 20.0 MW
Bondada Engineering Bags New Order from Gujarat Industries Power Company Ltd
Bondada received a GIPCL LOI for a 20 MW/120 MWh Vanadium Redox Flow BESS EPC project at Vadodara. No rupee value disclosed; 18-month completion timeline.
- From
- Gujarat Industries Power Company Ltd (GIPCL)
- Execution
- 18 months from receipt of NOA, plus 10 years O&M
- VRFB BESS power capacity (120 MWh storage)
- 20 MW
Bondada Engineering Other Announcement
The company submitted its quarterly shareholding pattern statement for the period ended September 30, 2026, in compliance with SEBI Regulation 31(1)(b).
Bondada Engineering SME to Main Board Migration
Bondada Engineering received NSE in-principle approval to migrate from BSE SME to NSE Main Board. BSE had granted its own approval earlier in September 2026.
Bondada Engineering Bags ₹1,154 Cr Order
Bondada Engineering received a ₹1,153.93 Crore EPC order for a 270 MWp solar project in Maharashtra. The related-party contract has a 6-month execution timeline.
- Value
- ₹1,154 Cr
- Execution
- 6 months from receipt of the order
- solar EPC capacity
- 270 MWp
Other production started announcements
All →EPack Prefab Technologies Production Started
EPACK Prefab commenced commercial production at its Ghiloth, Rajasthan facility effective October 28, 2026, adding 11,300 MT/annum of PEB capacity and 8,00,000 sq m/annum of PUF capacity. The project cost of around INR 100 Crore is not treated as an event value.
- PEB structures manufacturing capacity
- 11300.0 MT/annum
Zelio E-Mobility Production Started
Zelio E-Mobility began commercial production at its new Patan, Hisar plant on October 28, 2026. The plant adds 72,000 annual units of two- and three-wheeler capacity.
- manufacturing capacity (two- and three-wheelers)
- 72000.0 units per annum
Subros Production Started
Subros started commercial production at its new Kharkhoda greenfield plant on 28 October 2026. The plant adds 4.5 lakh units per annum of HVAC and hose capacity.
- HVAC and hose & tubes manufacturing capacity
- 4.5 lakh units per annum
ACME Solar Holdings Production Started
ACME Solar's subsidiary commissioned 35.77 MW/143.08 MWh of BESS capacity, bringing cumulative commissioned capacity to 195.35 MW/781.40 MWh. Commercial operation is scheduled for October 29, 2026.
- BESS discharge capacity commissioned
- 35.77 MW
Kalana Ispat Production Started
Kalana Ispat has commenced commercial production of alloy steel round bars at its new Khengaria rolling mill. The mill has an annual capacity of about 65,000 MT.
- alloy steel rolling mill capacity
- 0.065 MTPA
Jainik Power Cables Production Started
Jainik Power Cables commissioned a 400 kW solar plant at its Sonipat facility in October 2026. The installation supports energy efficiency and its ESR sustainability commitments.
- solar power plant capacity
- 400 kW